Thursday, August 13, 2015

Interior Trim

Interior trim and doors were installed today. The builder said the scheduled contractors that were supposed to start our flatwork today, no showed. So there's another delay. Also, the cabinet in the master bath is six inches too long. Again, another delay to anticipate.

Lunch photos:
Attic door











Afternoon photos:
Wrong measurement




























Posted by Jerry Markham at 9:43 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

About Me

My photo
Jerry Markham
View my complete profile

Blog Archive

  • ▼  2015 (123)
    • ►  October (2)
    • ►  September (21)
    • ▼  August (20)
      • Tile Part 2 - Some Grout
      • Tile Part 1 - Ceramic Tile
      • Back Fill & Countertops
      • A/C Pad and Grading Soil
      • Notice to Vacate Submitted
      • Flatwork - Day #4
      • Flatwork - Day #3
      • Flatwork - Day #2
      • Flatwork - Day #1
      • Primer and Interior Paint
      • Interior Trim
      • Cabinet Staining and Exterior Paint
      • Flashing Finishing
      • Curb Removal
      • Garage Door & Curb Cutting for Removal
      • Cabinet Installation and Underground Electrical
      • Address Brick
      • Gas Line Installation
      • Another Electrical/Drywall Error - Walls Textured
      • Electrical/Drywall Error
    • ►  July (17)
    • ►  June (10)
    • ►  May (17)
    • ►  April (9)
    • ►  March (8)
    • ►  February (7)
    • ►  January (12)
  • ►  2014 (17)
    • ►  December (2)
    • ►  October (4)
    • ►  September (11)
Awesome Inc. theme. Powered by Blogger.