Tuesday, August 4, 2015

Gas Line Installation

Cabinets were originally supposed to arrive today but I was updated that they wouldn't arrive until Thursday. However, the gas line was placed today.


Posted by Jerry Markham at 8:25 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

About Me

My photo
Jerry Markham
View my complete profile

Blog Archive

  • ▼  2015 (123)
    • ►  October (2)
    • ►  September (21)
    • ▼  August (20)
      • Tile Part 2 - Some Grout
      • Tile Part 1 - Ceramic Tile
      • Back Fill & Countertops
      • A/C Pad and Grading Soil
      • Notice to Vacate Submitted
      • Flatwork - Day #4
      • Flatwork - Day #3
      • Flatwork - Day #2
      • Flatwork - Day #1
      • Primer and Interior Paint
      • Interior Trim
      • Cabinet Staining and Exterior Paint
      • Flashing Finishing
      • Curb Removal
      • Garage Door & Curb Cutting for Removal
      • Cabinet Installation and Underground Electrical
      • Address Brick
      • Gas Line Installation
      • Another Electrical/Drywall Error - Walls Textured
      • Electrical/Drywall Error
    • ►  July (17)
    • ►  June (10)
    • ►  May (17)
    • ►  April (9)
    • ►  March (8)
    • ►  February (7)
    • ►  January (12)
  • ►  2014 (17)
    • ►  December (2)
    • ►  October (4)
    • ►  September (11)
Awesome Inc. theme. Powered by Blogger.