Thursday, July 30, 2015

Drywall - Day #3

Today the remaining seams, nails, screws, joints, corners, etc. were smoothed over. Also, I noticed many electrical markers in the front yard in preparation for flatwork.


Wednesday, July 29, 2015

Drywall - Day #2

I took some photo this morning of yesterday's work.























At lunch there was a two man crew smoothing over things. Tap embedding, puddy, stilts and applying rounded corners. Here are a couple of photos and a walkthrough video.




Tuesday, July 28, 2015

Drywall - Day #1

The builder has finally admitted that they will never make the mid August deadline. There is just too much to do because of all of the delays. Now they are saying 3rd week of September.

Lunch photos: I didn't know what was up with all of the insulation that showed up just before lunch. It wasn't there this morning. I later realized this insulation would be used in the ceiling.











Afternoon photos: There must have been 6-8 guys working